Section 1 Executive Summary
In February
1999, Johnson County Public Works retained Camp Dresser & McKee Inc. (CDM)
to complete the Blue River Watershed Study. The Blue River Watershed Study is
the first in a series of watershed studies conducted by Johnson County’s
Stormwater Management Program (SMP). This watershed was given the highest
priority, because a majority of the basin is undeveloped and expected to
experience significant growth in upcoming years. This study, funded entirely by
the SMP, has a scope of work based on the Tomahawk Creek Watershed Study,
completed by Overland Park in 1997.
The study area
includes that portion of the Blue River Watershed defined by the contributing
drainage area to the point where the Blue River exits Johnson County, approximately
4,600 feet north of the south Jackson County boundary line as shown in Figure
ES-i. The study area within the County is divided into six major subwatersheds,
including Blue River Main, Blue River North, Negro Creek, Coffee Creek, Wolf
Creek, and Camp Branch. The entire drainage area is approximately 86 square
miles, with approximately 76 square miles located in Johnson County. As shown
in Figure ES-2, the drainage area within the County encompasses portions of
four major government entities, including Johnson County and the cities of
Leawood, Olathe, and Overland Park. The study had the following multiple
objectives:
• Develop 100-year floodplain boundaries for current and future
conditions.
Floodplain
boundaries have been developed, up to 160-acre tributary area, for both current
development conditions and conditions that may occur in the future as the
watershed continues to develop. The current conditions 100-year floodplain
boundaries have been developed with the intent to submit to FEMA to replace
outdated FEMA maps for Johnson County. Future conditions 100-year floodplain
boundaries, also known as the planning condition scenario, have been developed
to provide an effective and proactive planning tool to manage future
development. With floodplain boundaries established prior to development, the
County and cities can significantly reduce flooding potential and need for
reactive stormwater improvements as the watershed continues to develop.
• Identify stormwater conveyance system inadequacies and develop
improvements.
The
criteria used to evaluate performance of the stormwater conveyance system
components were based ori existing regulations adopted by the County, cities,
and the Kansas Department of Transportation. Conveyance systems beneath roads
were analyzed for adequacy based on roadway classification — and for all roadway
classifications, the maximum allowable depth of stormwater overtopping the road
was 7-inches during the 100-year design storm. A total of 120 stormwater
conveyance structures, including 87 beneath arterial roads and 33 beneath
residential streets, were evaluated. Based on study criteria, 71 conveyance
structures
beneath arterial roads were identified as inadequate while 21 conveyance
structures beneath residential streets were identified as inadequate.
A
building was considered to be in the floodplain if the existing or planning 100-year floodplain intersected
the building. This requirement was applied to habitable buildings, which was
defined as buildings with regular long-term occupancy and sanitary sewer
facilities. Based on the above criteria, 65 habitable buildings were determined
to be in the 100-year
existing floodplain and an additional 15 buildings were determined to be in the
100-year planning conditions floodplain.
Because
of the watershed’s rural nature, a significant number of the conveyance system
components beneath unimproved roads were identified to not meet the study
criteria. As development occurs, it is anticipated that the majority of
undersized conveyance structures will be improved at the same time the road is
improved and widened to handle the increase in traffic flow. Therefore, for the
purposes of this study, improvement projects were not developed for the
majority of these undersized conveyance structures since detailed designs would
be completed at the time the roadway is upgraded. However, improvements were
developed for those undersized conveyance structures that were either causing
habitable building flooding, posed an immediate safety concern, or were
identified by the County or cities as high-priority projects. Additionally,
improvements were developed for locations where habitable buildings flooded,
and flooding was not caused by inadequate conveyance system components beneath
roads. The objective of the improvements was to develop a feasible planning
level conceptual solution.
Based
on input from the County and cities, the flooding problems identified as part
of this study were grouped into 19 improvement projects at a total estimated
probable cost of approximately $20 million. Figure ES-3 shows the general
location of each project. Table ES-i summarizes the number of projects and
costs for each subwatershed.
Table ES-i
___________________ Probable
Costs
Subwatershed Number of Projects Total Probable Project Costs
Negro Creek 4 $10,730,000
Coffee
Creek 2 $2,755,000
Wolf Creek 4 $870,000
Camp Branch 1 $65,000
Blue River
Main 8 $5,580,000
Blue River
North 0 $0
Total
19 $20,000,000
• Develop
hydrologic and hydraulic models and GIS datasets.
Strict
requirements for the computer models and GIS data sets were to provide a
deliverable that can be regularly maintained and updated to keep current
development conditions model “current.”
A
computer model review evaluation was conducted to identify appropriate
stormwater computer models to be used for this study, and for future County
evaluations. The evaluation resulted in selection of U.S. Army Corp of
Engineers (USACE) HEC-1 (version 4.0, September 1990) and HEC-RAS (version 2.2,
September 1998) computer models. Using these two models, a detailed hydrologic
and hydraulic analysis was conducted of the study area. The HEC-1 model was
used to estimate stormwater runoff flow rates from each subarea, and to route
flows downstream. The HEC-RAS model was used to simulate stormwater flowing in
the channels and drainage structures, and to estimate floodplain water surface
elevations based On existing and potential future landuse conditions. Detailed
floodplain maps at a scale of 1 inch = 200 feet, were submitted under separate cover to the County and cities.
The
Environmental Systems Research Institute’s (ESRI) software Arclnfo (version 7.2.x) and ArcView (version 3.2) applications were
required to utilize Johnson County’s extensive Geographic Information System
(GIS) datasets provided by the Automated Information Mapping System (AIMS)
Department. The GIS datasets were used to develop data inputs for the HEC-1 and
HEC-RAS models and automate the floodplain delineation process. The floodplain
automation process was accomplished using HEC-GeoRAS (version 1.0), which is a
software application that works directly with Arclnfo. Graphic and attribute data collected and developed for the
project were organized and stored in a database structure designed as part of
the project. The graphic data was stored in Arclnfo
while the attribute data was stored in Microsoft’s SQLServer (version 7.0)
relational database.
• Conduct a
public input/education program.
The
intent of the public involvement program was to encourage residents in the
watershed, particularly those who live along the channels, to become actively
involved in the study. A questionnaire was mailed out that described the
prOject and requested comments and input from landowners regarding existing
flooding problems. A total of 1,328 questionnaires were mailed to residents
located adjacent to the river and 147 responses were received, representing a
return rate of 11 percent. As a follow-up to the stormwater questionnaire, a
public meeting was held to inform and educate residents about the study and to
gather information about existing problems. It is expected an additional public
meeting will be held in the future to present final study results.
• Include
additional reference points to the Johnson County horizontal and vertical
control network and perform detailed system surveying.
CDM
retained Cook Flatt & Strobel Engineers (CFSE) to conduct a field survey of
the stormwater conveyance system as defined in Section 8.3 — Primary Stream Network. The
survey consisted of obtaining necessary data regarding physical characteristics
for each drainage structure, establishing benchmarks along major stream
crossings, and obtaining the lowest elevation along the perimeter of habitable
buildings adjacent to the channel where water could enter the structure. The
survey information was used to develop the computer model of the stormwater
conveyance system.
• Identify known/mapped outfall locations and evaluate best
management practice~
These
tasks were completed to assist Johnson County and the cities with compliance of
EPA’s pending Phase II Stormwater National Pollutant Discharge Elimination
System (NPDES) Regulations. Although compliance is not officially required
until March 8, 2003, the work completed as part of this study will move the
County and cities closer towards meeting the requirements of the regulations.